Peab has been commissioned to do the land and concrete work for Vindkraftpark Stor-Rotliden in Fredrika, Åsele. Peab has received the order from Vattenfall and the value of the contract is over SEK 100 million.
The contract comprises 40 wind generator foundations, crane parking spaces, roads and cable work. The work will commence at once and is expected to be completed in October 2010. When the wind power plant is up and running it will supply around 50,000 homes with renewable household electricity.
Peab AB discloses the information provided herein pursuant to the Securities Markets Act and/or the Financial Instruments Trading Act.
The information was submitted for publication at 10.00 a.m. on 1 July 2009.
|